How long does a
rebrand take?

Three to six weeks for most identity projects, three to six months for a full rebrand with rollout. The gap between those two numbers is almost entirely about scope and approvals.

Krayon Medias · 7 min read · 1 September 2026

How long branding and rebranding projects actually take — stage by stage, what makes them run late, and how to

Typical timelines

  1. Logo only — 1 to 2 weeks. Concepts in about a week, refinement after.
  2. Logo and guidelines — 3 to 4 weeks.
  3. Full brand identity — 4 to 8 weeks including applications.
  4. Identity with strategy and naming — 8 to 12 weeks.
  5. Full rebrand with rollout — 3 to 6 months, sometimes longer for multi-outlet businesses.

Rollout is the part people forget. Designing the new identity is a fraction of the work; replacing signage, packaging, uniforms, listings, documents and every existing asset is the rest.

Where the time actually goes

Discovery — 3 to 7 days

Business, audience, market, competitors, and what the brand has to achieve. Skipping this is the most common way projects run late, because the work has nothing to be judged against.

Direction — 5 to 10 days

Territories and concepts. Usually three directions, narrowed to one.

Refinement — 5 to 10 days

The chosen route developed properly. Two rounds of revisions is standard.

System and guidelines — 7 to 14 days

Colour, type, imagery, spacing, misuse, and the written rules.

Applications — varies enormously

Stationery is days. Packaging across a range is weeks. Signage depends on a fabricator you do not control.

Almost every late project was late because of approvals, not design.

The five things that cause delay

  1. Too many approvers. Three people with equal authority is the most reliable way to add a month.
  2. Slow feedback. A studio can turn a round in two days. If feedback takes ten, the timeline triples and none of it is production time.
  3. Scope added mid-project. "Can you also do the packaging" is a new project, not a revision.
  4. Content that does not exist yet. Design waits on copy, product photography and specifications more often than anyone expects.
  5. Vendors outside the project. Printers, fabricators and developers run on their own schedules.

How to keep it on schedule

Name one decision-maker before the project starts. Agree a feedback turnaround — 48 hours is reasonable. Consolidate comments into one response rather than sending them as they occur. And be honest at the brief about what does not exist yet, so it can be scheduled rather than discovered.

When to start

Work backwards from the date it has to be live. For a launch, a festive season or a funding round, start at least twice as far out as the design estimate — the second half is always rollout, printing and the things nobody listed.

Common questions

How long does logo design take?

One to two weeks for concepts and refinement, assuming feedback arrives promptly. Adding guidelines takes it to three or four weeks.

How long does a full rebrand take?

Three to six months including rollout. The design phase is usually six to twelve weeks; the rest is replacing existing assets across every touchpoint.

Can branding be done faster?

Yes, with a narrower scope, one decision-maker and fast feedback. Rush delivery is possible at a premium, but compressing discovery usually costs more later than it saves.